the work and progress of the construction of dome number 2
 
MAR 2015 - post for telescope stand erected
- footings and wall construction
 - cutting out door access

- 1st fit wiring
 - control wiring for telescope installed
 - fitting wooden floor

 

 - 2nd fit wiring
Dec 30 - fitting main access door [2016]
Dec 30 - fitting dome access door
Dec 30 - fitting roof
Jan 3 -  prepared floor [2017]
Jan 10 - fitted floor
Jan 31 - dome base cut formed and welded
Feb 17 - outside rendered

 - Telescope mount fitted and welded


Feb 22 - dome petals cut out and formed
Mar 3  - dome fitted to building roof
Mar 7  - dome door constructed
Apr 14 - control wiring for telescope completed
May 16 - plaster boarding
May 18 - plastering
May 22 - painted

Jun 9 - carpets fitted
Jun 27 - ceiling carpeted to cushion heads

- cupboards fitted